CONSTITUENCY BRIEFING · ENERGYMAP.APP

York Outer

MP: Mr Luke Charters (Labour) England Data to July 2026

York Outer has 42 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 15,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,162 homes.

Ranks 157 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
East York Energy HubYork Energy Park Limited Battery
250 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Murton Way - Battery Energy StorageFirst Way Solar Limited Battery
100 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Monets Garden Battery, Osbaldwick - Energy Storage FMonets Garden Battery Limited Battery
50 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.