Power one decision
could release
Projects held up by something a named organisation could act on: a refusal, a planning decision that is overdue, or a grid connection date. Projects with no recorded hold-up are left out, because there is nobody obvious to ask. Every row links to that constituency's briefing, which names the projects and drafts the questions.
Every constituency
| # | Constituency | MW that could be released | Who can move it | What is holding it up |
|---|---|---|---|---|
| 1 | Inverness, Skye and West Ross-shire | 8,447 | the Scottish Government (it decides big energy projects) | Waiting 1.3 years for a planning decision |
| 2 | Dumfriesshire, Clydesdale and Tweeddale | 5,918 | the Scottish Government (it decides big energy projects) | Waiting 1.2 years for a planning decision |
| 3 | Caithness, Sutherland and Easter Ross | 3,324 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 4 | Newark | 3,300 | the Planning Inspectorate (it decides nationally significant projects) | Waiting 1.1 years for a planning decision |
| 5 | Sleaford and North Hykeham | 2,750 | North Kesteven Council | Waiting 1.2 years for a planning decision |
| 6 | Argyll, Bute and South Lochaber | 2,462 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2030, 7 years after it was approved |
| 7 | Berwickshire, Roxburgh and Selkirk | 2,335 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2026, 3 years after it was approved |
| 8 | Gordon and Buchan | 1,824 | the developer and the network company | Approved a year ago — nothing has happened since |
| 9 | Doncaster North | 1,728 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 10 | Easington | 1,640 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2035 |
| 11 | Aberdeenshire North and Moray East | 1,355 | the Scottish Government (it decides big energy projects) | Waiting 1.1 years for a planning decision |
| 12 | Kettering | 1,303 | North Northamptonshire Council | Waiting 1.0 years for a planning decision |
| 13 | Ayr, Carrick and Cumnock | 1,286 | the developer and the network company | Approved a year ago — nothing has happened since |
| 14 | Daventry | 1,276 | the Planning Inspectorate (it decides nationally significant projects) | Waiting 1.1 years for a planning decision |
| 15 | South Derbyshire | 1,208 | the developer and the network company | Approved a year ago — nothing has happened since |
| 16 | Gainsborough | 1,200 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2029, 5 years after it was approved |
| 17 | Selby | 1,180 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2032, 7 years after it was approved |
| 18 | Dumfries and Galloway | 1,129 | the Scottish Government (it decides big energy projects) | Waiting 1.4 years for a planning decision |
| 19 | Brigg and Immingham | 1,097 | North Lincolnshire Council | Waiting 1.1 years for a planning decision |
| 20 | Richmond and Northallerton | 1,073 | North Yorkshire Council | Waiting 1.6 years for a planning decision |
| 21 | South Norfolk | 1,043 | South Norfolk Council | Waiting 1.0 years for a planning decision |
| 22 | Waveney Valley | 1,012 | Mid Suffolk Council | Waiting 1.1 years for a planning decision |
| 23 | Paisley and Renfrewshire South | 950 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 24 | North East Hertfordshire | 944 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2034, 9 years after it was approved |
| 25 | Mid Norfolk | 901 | Breckland Council | Waiting 1.1 years for a planning decision |
| 26 | Bicester and Woodstock | 854 | the Planning Inspectorate (it decides nationally significant projects) | Waiting 1.7 years for a planning decision |
| 27 | Lothian East | 815 | the developer and the network company | Approved a year ago — nothing has happened since |
| 28 | Stretford and Urmston | 800 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2028, 3 years after it was approved |
| 29 | Angus and Perthshire Glens | 780 | the developer and the network company | Approved a year ago — nothing has happened since |
| 30 | Moray West, Nairn and Strathspey | 714 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 31 | Inverclyde and Renfrewshire West | 701 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2029, 5 years after it was approved |
| 32 | Vale of Glamorgan | 689 | Vale of Glamorgan Council | Waiting 1.2 years for a planning decision |
| 33 | South Holland and The Deepings | 628 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2033, 10 years after it was approved |
| 34 | Alloa and Grangemouth | 625 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 35 | Kilmarnock and Loudoun | 610 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 36 | Buckingham and Bletchley | 601 | the grid operator (NESO) | Still in the grid queue review — no firm connection date yet |
| 37 | Grantham and Bourne | 581 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2028, 3 years after it was approved |
| 38 | Bassetlaw | 575 | Bassetlaw Council | Waiting 1.2 years for a planning decision |
| 39 | Honiton and Sidmouth | 570 | East Devon Council | Refused by East Devon Council in 2025 |
| 40 | North West Essex | 562 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2028, 5 years after it was approved |
| 41 | Airdrie and Shotts | 562 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 42 | Chester South and Eddisbury | 537 | Cheshire West and Chester Council | Waiting 4.4 years for a planning decision |
| 43 | Perth and Kinross-shire | 529 | the Scottish Government (it decides big energy projects) | Waiting 2.2 years for a planning decision |
| 44 | Mid Buckinghamshire | 516 | Buckinghamshire Council | Waiting 1.3 years for a planning decision |
| 45 | Staffordshire Moorlands | 502 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 46 | Alyn and Deeside | 500 | Flintshire Council | Waiting 1.2 years for a planning decision |
| 47 | Montgomeryshire and Glyndwr | 487 | Wrexham Council | Waiting 2.4 years for a planning decision |
| 48 | Chippenham | 460 | Wiltshire Council | Waiting 1.1 years for a planning decision |
| 49 | Goole and Pocklington | 445 | the grid operator (NESO) | Still in the grid queue review — no firm connection date yet |
| 50 | Stirling and Strathallan | 430 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2031, 6 years after it was approved |
| 51 | Warrington South | 427 | Warrington Council | Refused by Warrington Council in 2025 |
| 52 | Orkney and Shetland | 420 | the grid operator (NESO) and SSEN Transmission | Cannot connect to the grid until 2032, 9 years after it was approved |
| 53 | Old Bexley and Sidcup | 412 | Bexley Council | Waiting 1.2 years for a planning decision |
| 54 | Doncaster East and the Isle of Axholme | 400 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2029 |
| 55 | South Basildon and East Thurrock | 368 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 56 | Midlothian | 358 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2031, 6 years after it was approved |
| 57 | Dunstable and Leighton Buzzard | 350 | Central Bedfordshire Council | Refused by Central Bedfordshire Council in 2025 |
| 58 | Carlisle | 340 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 59 | Pontypridd | 331 | Rhondda Cynon Taf Council | Waiting 1.1 years for a planning decision |
| 60 | Witney | 321 | West Oxfordshire Council | Waiting 1.0 years for a planning decision |
| 61 | Skipton and Ripon | 319 | North Yorkshire Council | Waiting 1.0 years for a planning decision |
| 62 | Meriden and Solihull East | 317 | the developer and the network company | Approved a year ago — nothing has happened since |
| 63 | Arbroath and Broughty Ferry | 307 | the grid operator (NESO) and SSEN Transmission | Cannot connect to the grid until 2027, 2 years after it was approved |
| 64 | Ashford | 300 | Ashford Council | Refused by Ashford Council in 2025 |
| 65 | Dartford | 300 | Dartford Council | Refused by Dartford Council in 2024 |
| 66 | North Ayrshire and Arran | 298 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 67 | Gower | 290 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 68 | Runcorn and Helsby | 282 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 69 | West Aberdeenshire and Kincardine | 259 | the Scottish Government (it decides big energy projects) | Waiting 2.7 years for a planning decision |
| 70 | Horsham | 257 | the developer and the network company | Approved a year ago — nothing has happened since |
| 71 | North East Hampshire | 257 | Basingstoke and Deane Council | Refused by Basingstoke and Deane Council in 2026 |
| 72 | Burnley | 255 | the developer and the network company | Approved a year ago — nothing has happened since |
| 73 | Foyle | 240 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 74 | West Tyrone | 238 | Fermanagh and Omagh Council | Waiting 1.6 years for a planning decision |
| 75 | East Antrim | 230 | Mid and East Antrim Council | Waiting 3.1 years for a planning decision |
| 76 | Bexhill and Battle | 230 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 77 | Wells and Mendip Hills | 230 | North Somerset Council | Waiting 1.1 years for a planning decision |
| 78 | South Northamptonshire | 218 | North Northamptonshire Council | Refused by North Northamptonshire Council in 2025 |
| 79 | Central Suffolk and North Ipswich | 216 | the developer and the network company | Approved a year ago — nothing has happened since |
| 80 | East Kilbride and Strathaven | 213 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2030, 5 years after it was approved |
| 81 | Glenrothes and Mid Fife | 210 | the Scottish Government (it decides big energy projects) | Waiting 1.5 years for a planning decision |
| 82 | North East Cambridgeshire | 210 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 83 | Wetherby and Easingwold | 203 | the developer and the network company | Approved a year ago — nothing has happened since |
| 84 | Lichfield | 200 | Lichfield Council | Refused by Lichfield Council in 2026 |
| 85 | Spelthorne | 200 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2031, 5 years after it was approved |
| 86 | Stockton North | 200 | Stockton-on-Tees Council | Waiting 1.5 years for a planning decision |
| 87 | Glasgow North East | 200 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 88 | Hamilton and Clyde Valley | 200 | the Scottish Government (it decides big energy projects) | Waiting 1.5 years for a planning decision |
| 89 | Mid Dunbartonshire | 200 | the developer and the network company | Approved a year ago — nothing has happened since |
| 90 | Merthyr Tydfil and Aberdare | 200 | Rhondda Cynon Taf Council | Waiting 1.2 years for a planning decision |
| 91 | West Dunbartonshire | 199 | the Scottish Government (it decides big energy projects) | Waiting 1.6 years for a planning decision |
| 92 | North East Fife | 177 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2022, 2 years after it was approved |
| 93 | Weald of Kent | 176 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 94 | Dwyfor Meirionnydd | 171 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 95 | Ely and East Cambridgeshire | 170 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 96 | Aberdeen North | 170 | the developer and the network company | Approved a year ago — nothing has happened since |
| 97 | Fylde | 163 | Fylde Council | Waiting 1.1 years for a planning decision |
| 98 | Paisley and Renfrewshire North | 162 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2030, 7 years after it was approved |
| 99 | Rugby | 162 | the developer and the network company | Approved a year ago — nothing has happened since |
| 100 | St Austell and Newquay | 153 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 101 | Coventry East | 153 | Coventry Council | Waiting 1.0 years for a planning decision |
| 102 | Havant | 150 | Havant Council | Waiting 1.3 years for a planning decision |
| 103 | Rayleigh and Wickford | 150 | the developer and the network company | Approved a year ago — nothing has happened since |
| 104 | Edinburgh South West | 150 | the Scottish Government (it decides big energy projects) | Waiting 1.4 years for a planning decision |
| 105 | Henley and Thame | 150 | South Oxfordshire Council | Refused by South Oxfordshire Council in 2025 |
| 106 | Rushcliffe | 150 | the developer and the network company | Approved a year ago — nothing has happened since |
| 107 | Stroud | 150 | Stroud Council | Refused by Stroud Council in 2023 |
| 108 | West Worcestershire | 150 | Malvern Hills Council | Waiting 1.7 years for a planning decision |
| 109 | Corby and East Northamptonshire | 148 | North Northamptonshire Council | Waiting 2.9 years for a planning decision |
| 110 | East Hampshire | 147 | East Hampshire Council | Refused by East Hampshire Council in 2024 |
| 111 | Forest of Dean | 147 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 112 | Rother Valley | 143 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 113 | Newport East | 143 | Welsh Government (NSIP) Council | Refused by Welsh Government (NSIP) Council in 2025 |
| 114 | East Londonderry | 130 | Derry City and Strabane Council | Waiting 3.6 years for a planning decision |
| 115 | Rutherglen | 130 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 116 | Aberafan Maesteg | 130 | Welsh Government (NSIP) Council | Refused by Welsh Government (NSIP) Council in 2025 |
| 117 | Amber Valley | 129 | Amber Valley Council | Refused by Amber Valley Council in 2022 |
| 118 | Beaconsfield | 129 | Buckinghamshire Council | Waiting 1.0 years for a planning decision |
| 119 | Melton and Syston | 127 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 120 | Wycombe | 126 | Buckinghamshire Council | Waiting 2.7 years for a planning decision |
| 121 | Shrewsbury | 125 | Shropshire Council | Waiting 1.4 years for a planning decision |
| 122 | Hexham | 122 | Newcastle upon Tyne Council | Waiting 2.2 years for a planning decision |
| 123 | Brecon, Radnor and Cwm Tawe | 121 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2037, 13 years after it was approved |
| 124 | Barking | 120 | Barking and Dagenham Council | Waiting 2.3 years for a planning decision |
| 125 | Portsmouth North | 120 | Portsmouth Council | Waiting 1.0 years for a planning decision |
| 126 | West Lancashire | 120 | the developer and the network company | Approved a year ago — nothing has happened since |
| 127 | Livingston | 117 | the developer and the network company | Approved a year ago — nothing has happened since |
| 128 | Stone, Great Wyrley and Penkridge | 114 | the developer and the network company | Approved a year ago — nothing has happened since |
| 129 | Wrexham | 114 | Welsh Government (NSIP) Council | Waiting 2.1 years for a planning decision |
| 130 | North Dorset | 112 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2036, 13 years after it was approved |
| 131 | Stafford | 110 | Stafford Council | Waiting 2.4 years for a planning decision |
| 132 | Rotherham | 110 | Rotherham Council | Waiting 1.0 years for a planning decision |
| 133 | South Ribble | 107 | the grid operator (NESO) | Cleared the grid queue review, so it now has a firm connection date |
| 134 | Normanton and Hemsworth | 102 | Wakefield Council | Waiting 4.1 years for a planning decision |
| 135 | South Cambridgeshire | 102 | South Cambridgeshire Council | Waiting 1.4 years for a planning decision |
| 136 | Torridge and Tavistock | 101 | the developer and the network company | Approved a year ago — nothing has happened since |
| 137 | Cannock Chase | 100 | Cannock Chase Council | Refused by Cannock Chase Council in 2026 |
| 138 | Kingswinford and South Staffordshire | 100 | South Staffordshire Council | Refused by South Staffordshire Council in 2025 |
| 139 | Maldon | 100 | Chelmsford Council | Refused by Chelmsford Council in 2022 |
| 140 | North West Norfolk | 100 | the developer and the network company | Approved a year ago — nothing has happened since |
| 141 | South Shropshire | 100 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 142 | Stoke-on-Trent South | 100 | Staffordshire Moorlands Council | Waiting 1.2 years for a planning decision |
| 143 | North Antrim | 100 | Causeway Coast and Glens Council | Waiting 1.4 years for a planning decision |
| 144 | Herne Bay and Sandwich | 100 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 145 | Glasgow South West | 100 | the developer and the network company | Approved a year ago — nothing has happened since |
| 146 | Dover and Deal | 99 | Dover Council | Waiting 1.1 years for a planning decision |
| 147 | South Devon | 99 | South Hams Council | Waiting 1.6 years for a planning decision |
| 148 | Frome and East Somerset | 99 | Somerset Council | Refused by Somerset Council in 2026 |
| 149 | Washington and Gateshead South | 98 | Gateshead Council | Refused by Gateshead Council in 2026 |
| 150 | Na h-Eileanan an Iar | 98 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 151 | North Cornwall | 94 | Cornwall Council | Refused by Cornwall Council in 2025 |
| 152 | West Suffolk | 93 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 153 | North Bedfordshire | 92 | the developer and the network company | Approved a year ago — nothing has happened since |
| 154 | Rossendale and Darwen | 85 | Rossendale Council | Refused by Rossendale Council in 2025 |
| 155 | South Cotswolds | 83 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2025, 1 years after it was approved |
| 156 | Arundel and South Downs | 82 | the developer and the network company | Approved a year ago — nothing has happened since |
| 157 | Newport West and Islwyn | 82 | Welsh Government (NSIP) Council | Waiting 1.2 years for a planning decision |
| 158 | Motherwell, Wishaw and Carluke | 80 | the grid operator (NESO) and SP Transmission | Cannot connect to the grid until 2028, 6 years after it was approved |
| 159 | Mid Dorset and North Poole | 80 | the grid operator (NESO) and National Grid | Cannot connect to the grid until 2025, 4 years after it was approved |
| 160 | Blaydon and Consett | 78 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 161 | Harpenden and Berkhamsted | 75 | St Albans Council | Waiting 1.1 years for a planning decision |
| 162 | Torfaen | 75 | Welsh Government (NSIP) Council | Waiting 1.4 years for a planning decision |
| 163 | Didcot and Wantage | 74 | the developer and the network company | Approved a year ago — nothing has happened since |
| 164 | Barrow and Furness | 72 | Westmorland and Furness Council | Waiting 1.4 years for a planning decision |
| 165 | Kenilworth and Southam | 70 | the developer and the network company | Approved a year ago — nothing has happened since |
| 166 | Mid Bedfordshire | 68 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 167 | South Antrim | 68 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 168 | Thornbury and Yate | 66 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 169 | Droitwich and Evesham | 66 | Wychavon Council | Waiting 2.1 years for a planning decision |
| 170 | Tonbridge | 65 | Sevenoaks Council | Waiting 1.5 years for a planning decision |
| 171 | North Warwickshire and Bedworth | 63 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 172 | Broadland and Fakenham | 63 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 173 | South Dorset | 62 | the developer and the network company | Approved a year ago — nothing has happened since |
| 174 | Clwyd North | 62 | Welsh Government (NSIP) Council | Refused by Welsh Government (NSIP) Council in 2022 |
| 175 | Epping Forest | 61 | Epping Forest Council | Refused by Epping Forest Council in 2026 |
| 176 | York Outer | 60 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 177 | Knowsley | 58 | Knowsley Council | Waiting 1.3 years for a planning decision |
| 178 | Hitchin | 57 | North Hertfordshire Council | Waiting 1.2 years for a planning decision |
| 179 | Harwich and North Essex | 54 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 180 | North West Hampshire | 51 | Basingstoke and Deane Council | Waiting 1.1 years for a planning decision |
| 181 | Blyth and Ashington | 50 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 182 | East Surrey | 50 | Tandridge Council | Waiting 1.1 years for a planning decision |
| 183 | Exmouth and Exeter East | 50 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 184 | North Herefordshire | 50 | Herefordshire, County of Council | Refused by Herefordshire, County of Council in 2024 |
| 185 | Oxford West and Abingdon | 50 | Vale of White Horse Council | Refused by Vale of White Horse Council in 2025 |
| 186 | Southend East and Rochford | 50 | Rochford Council | Waiting 2.9 years for a planning decision |
| 187 | Sutton Coldfield | 50 | Birmingham Council | Waiting 1.6 years for a planning decision |
| 188 | Warwick and Leamington | 50 | Warwick Council | Refused by Warwick Council in 2025 |
| 189 | Blaenau Gwent and Rhymney | 50 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 190 | Cardiff South and Penarth | 50 | the developer and the network company | Approved a year ago — nothing has happened since |
| 191 | Barnsley North | 50 | Barnsley Council | Waiting 1.5 years for a planning decision |
| 192 | Basildon and Billericay | 50 | Basildon Council | Refused by Basildon Council in 2023 |
| 193 | Bolsover | 50 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 194 | Christchurch | 50 | Bournemouth, Christchurch and Poole Council | Waiting 1.0 years for a planning decision |
| 195 | Hornchurch and Upminster | 50 | Havering Council | Waiting 5.3 years for a planning decision |
| 196 | Lewes | 50 | Wealden Council | Refused by Wealden Council in 2023 |
| 197 | Loughborough | 50 | Charnwood Council | Waiting 1.5 years for a planning decision |
| 198 | North Northumberland | 50 | the grid operator (NESO) and SSEN Transmission | Cannot connect to the grid until 2027, 3 years after it was approved |
| 199 | North West Leicestershire | 50 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 200 | Rutland and Stamford | 50 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 201 | Sevenoaks | 50 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 202 | Southampton Itchen | 50 | the developer and the network company | Approved a year ago — nothing has happened since |
| 203 | Tewkesbury | 50 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 204 | Belfast West | 50 | Belfast Council | Waiting 6.0 years for a planning decision |
| 205 | Dundee Central | 50 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 206 | Edinburgh South | 50 | City of Edinburgh Council | Waiting 2.4 years for a planning decision |
| 207 | North Cotswolds | 50 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 208 | St Neots and Mid Cambridgeshire | 46 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 209 | Bury St Edmunds and Stowmarket | 42 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 210 | North East Somerset and Hanham | 42 | the developer and the network company | Approved a year ago — nothing has happened since |
| 211 | Aylesbury | 40 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 212 | Banbury | 40 | Cherwell Council | Waiting 1.0 years for a planning decision |
| 213 | Salisbury | 40 | the developer and the network company | Approved 6 years ago — nothing has happened since |
| 214 | South Shields | 40 | South Tyneside Council | Waiting 2.1 years for a planning decision |
| 215 | Suffolk Coastal | 40 | East Suffolk Council | Waiting 1.1 years for a planning decision |
| 216 | South Down | 40 | Newry, Mourne and Down Council | Waiting 11.3 years for a planning decision |
| 217 | Witham | 39 | the developer and the network company | Approved a year ago — nothing has happened since |
| 218 | Westmorland and Lonsdale | 38 | the developer and the network company | Approved a year ago — nothing has happened since |
| 219 | Cowdenbeath and Kirkcaldy | 37 | the developer and the network company | Approved a year ago — nothing has happened since |
| 220 | East Wiltshire | 35 | Swindon Council | Waiting 1.2 years for a planning decision |
| 221 | Huntingdon | 35 | the developer and the network company | Approved a year ago — nothing has happened since |
| 222 | Taunton and Wellington | 34 | Somerset Council | Waiting 1.1 years for a planning decision |
| 223 | City of Durham | 32 | County Durham Council | Waiting 2.7 years for a planning decision |
| 224 | Folkestone and Hythe | 31 | Folkestone and Hythe Council | Waiting 1.3 years for a planning decision |
| 225 | Hazel Grove | 30 | the developer and the network company | Approved a year ago — nothing has happened since |
| 226 | Hertsmere | 30 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 227 | Penrith and Solway | 30 | the developer and the network company | Approved a year ago — nothing has happened since |
| 228 | South West Wiltshire | 30 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 229 | The Wrekin | 30 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 230 | Thirsk and Malton | 30 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 231 | Clacton | 29 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 232 | North Durham | 27 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 233 | Oldham East and Saddleworth | 27 | Oldham Council | Waiting 1.0 years for a planning decision |
| 234 | Tatton | 26 | Cheshire West and Chester Council | Waiting 1.4 years for a planning decision |
| 235 | Mid Ulster | 26 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 236 | Neath and Swansea East | 25 | Welsh Government (NSIP) Council | Waiting 1.3 years for a planning decision |
| 237 | Bathgate and Linlithgow | 24 | the developer and the network company | Approved a year ago — nothing has happened since |
| 238 | North West Cambridgeshire | 22 | the developer and the network company | Approved a year ago — nothing has happened since |
| 239 | Dorking and Horley | 22 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 240 | Hinckley and Bosworth | 22 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 241 | Glastonbury and Somerton | 21 | Somerset Council | Waiting 1.0 years for a planning decision |
| 242 | Scunthorpe | 20 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 243 | Burton and Uttoxeter | 20 | East Staffordshire Council | Waiting 1.0 years for a planning decision |
| 244 | South Leicestershire | 20 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 245 | Yeovil | 18 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 246 | Central Ayrshire | 18 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 247 | New Forest East | 17 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 248 | Mid and South Pembrokeshire | 17 | the developer and the network company | Approved a year ago — nothing has happened since |
| 249 | Bridgwater | 17 | the developer and the network company | Approved a year ago — nothing has happened since |
| 250 | Broxtowe | 16 | the developer and the network company | Approved a year ago — nothing has happened since |
| 251 | Doncaster Central | 16 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 252 | Welwyn Hatfield | 16 | Welwyn Hatfield Council | Waiting 1.1 years for a planning decision |
| 253 | Faversham and Mid Kent | 15 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 254 | Lancaster and Wyre | 15 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 255 | Melksham and Devizes | 15 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 256 | North Somerset | 15 | the developer and the network company | Approved a year ago — nothing has happened since |
| 257 | East Renfrewshire | 15 | the developer and the network company | Approved a year ago — nothing has happened since |
| 258 | Cardiff East | 15 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 259 | Godalming and Ash | 14 | Waverley Council | Waiting 5.7 years for a planning decision |
| 260 | West Dorset | 12 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 261 | Fareham and Waterlooville | 10 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 262 | Runnymede and Weybridge | 10 | Runnymede Council | Waiting 1.0 years for a planning decision |
| 263 | Lowestoft | 10 | East Suffolk Council | Refused by East Suffolk Council in 2024 |
| 264 | Winchester | 10 | the developer and the network company | Approved a year ago — nothing has happened since |
| 265 | Worsley and Eccles | 10 | Wigan Council | Waiting 1.9 years for a planning decision |
| 266 | Blackpool North and Fleetwood | 9.3 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 267 | Strangford | 8.8 | Ards and North Down Council | Waiting 2.2 years for a planning decision |
| 268 | Hertford and Stortford | 7.3 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 269 | Rhondda and Ogmore | 7.2 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 270 | Ashfield | 7 | Ashfield Council | Refused by Ashfield Council in 2026 |
| 271 | Chester North and Neston | 5 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 272 | Milton Keynes North | 5 | Milton Keynes Council | Refused by Milton Keynes Council in 2024 |
| 273 | North Shropshire | 5 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 274 | Lagan Valley | 5 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 275 | Hartlepool | 4.3 | the developer and the network company | Approved 4 years ago — nothing has happened since |
| 276 | Tiverton and Minehead | 4.3 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 277 | Belfast North | 4.1 | Belfast Council | Refused by Belfast Council in 2021 |
| 278 | Newton Aycliffe and Spennymoor | 3.3 | the developer and the network company | Approved a year ago — nothing has happened since |
| 279 | South West Hertfordshire | 3 | Three Rivers Council | Waiting 3.8 years for a planning decision |
| 280 | Widnes and Halewood | 3 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 281 | Greenwich and Woolwich | 2.9 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 282 | Surrey Heath | 2.4 | Surrey Heath Council | Refused by Surrey Heath Council in 2024 |
| 283 | Rawmarsh and Conisbrough | 2.1 | the developer and the network company | Approved 9 years ago — nothing has happened since |
| 284 | Windsor | 2 | Slough Council | Refused by Slough Council in 2024 |
| 285 | Belfast South and Mid Down | 2 | the developer and the network company | Approved 7 years ago — nothing has happened since |
| 286 | Llanelli | 1.6 | the developer and the network company | Approved 5 years ago — nothing has happened since |
| 287 | Maidenhead | 1.3 | the developer and the network company | Approved 2 years ago — nothing has happened since |
| 288 | New Forest West | 1.3 | the developer and the network company | Approved a year ago — nothing has happened since |
| 289 | Stratford-on-Avon | 1.2 | the developer and the network company | Approved 3 years ago — nothing has happened since |
| 290 | Hammersmith and Chiswick | 1 | Hammersmith and Fulham Council | Waiting 3.1 years for a planning decision |
| 291 | Liverpool Walton | 1 | Liverpool Council | Waiting 3.1 years for a planning decision |
| 292 | North Devon | 1 | the developer and the network company | Approved less than a year ago — nothing has happened since |
| 293 | Warrington North | 1 | the developer and the network company | Approved less than a year ago — nothing has happened since |