York Outer
York Outer has 42 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 15,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,162 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Hessay Solar Farm | Solar Photovoltaics | 15,000 homes | 40.0 MW | 2024-03 | 2.4 yrs |
| Naburn Weir Hydro | Small Hydro | 600 homes | 0.5 MW | 2020-01 | 6.5 yrs |
| Walbutts Sewage Works, Brecks Lane - Solar Array | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-09 | 2.8 yrs |
| Newlands Farm, Wigginton - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2024-05 | 2.2 yrs |
| Haggwood Farm, Broad Highway - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-04 | 3.3 yrs |
| Westhouse Farm, Elvington - Solar Array | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-04 | 3.3 yrs |
Plus 9 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| East York Energy Hub | 250 MW | approved, not built 2025 | could supply ≈876,000 homes |
| Murton Way - Battery Energy Storage | 100 MW | approved, not built 2025 | could supply ≈350,000 homes |
| Monets Garden Battery, Osbaldwick - Energy Storage Facility | 50 MW | approved, not built 2025 | could supply ≈175,000 homes |
| Osbaldwick Substation | 50 MW | 2020 | could supply ≈175,000 homes |
| Meadowville, Hull Road - Battery Energy Storage System | 48 MW | approved, not built 2025 | could supply ≈168,000 homes |
| Sutton-on-the-Forest, Brownmoor Lane -BESS | 10 MW | in planning | could supply ≈35,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Mr Luke Charters said about the grid in Parliament? Search Hansard →