Thirsk and Malton has 7.2 MW of clean power (mostly solar) approved and still not built: enough to supply a year's electricity to 4,100 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,580 homes.

Ranks 241 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Third Energy UK Gas Limited - Battery Energy StorageThird Energy Battery
100 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company
Windmill Farm Solar Farm (Old Malton)Harmony Energy Solar 11,000 homes
30 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Stell Solar FarmEnviromena Solar 11,000 homes
30 MW
Waiting 1.0 years for a planning decisionWho can move it: North Yorkshire Council