Goole and Pocklington has 63 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 27,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,355 homes. There is also 140 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 107 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Thornton Battery StorageGreenfield Energy Developments Limited Battery
400 MW
Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO)
East Yorkshire Solar FarmBoom Power Solar 145,000 homes
400 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Ryedale Farm, Seaton Common Lane - Battery Energy StRPC Elmya Carnation Foxdale Limited Battery
300 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company