Selby has 190 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 69,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,292 homes. There is also 34 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 23 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Eggborough Battery Energy Storage SystemSSE Renewables Ireland Limited Battery
550 MW
Cannot connect to the grid until 2032, 7 years after it was approvedWho can move it: the grid operator (NESO) and National Grid
Light Valley Solar, Selby Road - Solar FarmLight Valley Solar Limited ( Island Green Powe Solar 182,000 homes
500 MW
Applied in 2026, still waiting for a decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects)
Eggborough Power Station, Selby Road - Battery StoraEggborough Power Limited Battery
500 MW
Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company