Paisley and Renfrewshire North

MP: Alison Taylor (Labour) Scotland Data to July 2026

Paisley and Renfrewshire North has 15 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 5,600 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £5.0m across the constituency's 43,222 homes. A 50 MW battery was refused planning here in 2024; while discharging it could have supplied about 175,000 homes.

Ranks 223 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
East Fulwood Energy StorageLightsourcebp Battery 400 MW Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006230
Barnwell, Wright Street - Battery Energy StorageP3P Partners Llp Battery 50 MW Refused by Renfrewshire Council in 2024Who can move it: Renfrewshire Council · planning ref 24/0153/PP
Laigh Park Water Treatment Works - Battery Energy Storage SystemBluestone Energy Battery 50 MW Applied in 2025, still waiting for a decisionWho can move it: Renfrewshire Council · planning ref 25/0779/PP
South Clyde Energy CentreFortum (formerly Peel Environmental) EfW Incineration 45 MW Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2026 · planning ref 12/01293/DC
East Fulwood Greenock Road - Solar FarmSpringfield Limited & Aggreko Solar 14 MW5,200 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/0582/PP

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Paisley and Renfrewshire North 15 MW20 MWnot visible
Paisley and Renfrewshire South 0 MW1.6 MWnot visible
Glasgow South West 1.1 MW0.2 MWnot visible
Inverclyde and Renfrewshire West 4.3 MW24 MWnot visible

Paisley and Renfrewshire North has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.