Paisley and Renfrewshire South
Paisley and Renfrewshire South has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 45,518 homes.
Ranks 569 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Neilston Greener Grid Park - Phase 2Statkraft UK LTD | Battery | 750 MW |
Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) |
| Neilston - Battery StorageApatura (GPC 1119 Ltd) | Battery | 150 MW |
Cannot connect to the grid until 2025Who can move it: the grid operator (NESO) and SP Transmission |
| Neilston Greener Grid ParkStatkraft UK LTD | Battery | 50 MW |
Under constructionWho can move it: the developer |
What else is in the briefing
- All 6 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Paisley and Renfrewshire South compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call