 "pcon24cd": "S14000101",
 "name": "Paisley and Renfrewshire North",
 "nation": "Scotland",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 102.5,
  "stuck_mw_int": 102,
  "stuck_sites": 7,
  "homes_equivalent": 72000,
  "homes_vs_seat_households": 1.66,
  "stuck_mw_12m_cut": 102.5,
  "consented_not_built_mw_any_age": 102.5,
  "operational_mw": 0.0,
  "operational_homes_equivalent": 0,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 4.9,
  "rank": 66,
  "tech_mix": {
   "onshore wind": 67.2,
   "solar": 35.3
  },
  "tech_summary": "mostly onshore wind",
  "waiting_vs_running": null,
  "projects": [
   {
    "site_name": "Artfield Forest Wind Farm",
    "repd_ref_id": 7871,
    "technology": "Wind Onshore",
    "capacity_mw": 67.2,
    "homes_equivalent": 59000,
    "consented": "2023-02-10",
    "months_waiting": 41.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Glasgow Airport Solar Farm",
    "repd_ref_id": 10549,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 19.9,
    "homes_equivalent": 7200,
    "consented": "2023-04-06",
    "months_waiting": 39.9,
    "status": "Under Construction"
   },
   {
    "site_name": "East Fulwood Greenock Road - Solar Farm",
    "repd_ref_id": 9946,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 14.3,
    "homes_equivalent": 5200,
    "consented": "2023-01-24",
    "months_waiting": 42.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Fifty Pitches Place - Solar Panels",
    "repd_ref_id": 14619,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2023-12-01",
    "months_waiting": 32.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Cartside Avenue, Inchinnan - Solar Panels",
    "repd_ref_id": 12519,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-02-09",
    "months_waiting": 41.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Cpi Medicines Manufacturing Centre, Netherton Square - Solar Panels",
    "repd_ref_id": 14352,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-01-30",
    "months_waiting": 30.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Decathlon, Old Govan Road - Solar Panels",
    "repd_ref_id": 15509,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-03-29",
    "months_waiting": 28.2,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 43222,
  "seat_total_gbp": 4000000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 29.9,
  "building_mw": 0.0,
  "approved_mw": 0.0,
  "approved_24m_mw": 0.0,
  "refused_mw": 49.9,
  "submitted_mw": 449.5,
  "sites": [
   {
    "site_name": "East Fulwood Energy Storage",
    "capacity_mw": 400.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 1402000
   },
   {
    "site_name": "Barnwell, Wright Street - Battery Energy Storage",
    "capacity_mw": 49.9,
    "status": "refused",
    "year": 2024,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Laigh Park Water Treatment Works - Battery Energy Storage System",
    "capacity_mw": 49.5,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 173000
   },
   {
    "site_name": "Land SW of Shilton Cottage",
    "capacity_mw": 29.9,
    "status": "operating",
    "year": null,
    "homes_while_discharging": 105000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "East Fulwood Energy Storage",
   "repd_ref_id": 19578,
   "technology": "Battery",
   "capacity_mw": 400.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00006230",
   "operator": "Lightsourcebp",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2026, still waiting for a decision",
    "who": "the Scottish Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2026-01-12",
     "months_waiting": 7
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Artfield Forest Wind Farm",
   "repd_ref_id": 7871,
   "technology": "Wind Onshore",
   "capacity_mw": 67.2,
   "homes_equivalent": 59000,
   "status": "Awaiting Construction",
   "consented": "2023-02-10",
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00003245",
   "operator": "Statkraft UK",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2030, 7 years after it was approved",
    "who": "the grid operator (NESO) and SP Transmission",
    "evidence": {
     "project": "Artfield Forest Wind Farm",
     "connection_date": "2030-06-28",
     "mw": 85.8,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2030",
   "tec": {
    "project": "Artfield Forest Wind Farm",
    "connection_date": "2030-06-28",
    "connection_year": 2030,
    "mw": 85.8,
    "stage": null,
    "who": "the grid operator (NESO) and SP Transmission",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Barnwell, Wright Street - Battery Energy Storage",
   "repd_ref_id": 16107,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Application Refused",
   "consented": null,
   "refused": "2024-05-28",
   "planning_authority": "Renfrewshire",
   "planning_ref": "24/0153/PP",
   "operator": "P3P Partners Llp",
   "reason": {
    "reason": "refused",
    "label": "Refused by Renfrewshire Council in 2024",
    "who": "Renfrewshire Council",
    "evidence": {
     "refusal_date": "2024-05-28"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Laigh Park Water Treatment Works - Battery Energy Storage System",
   "repd_ref_id": 12030,
   "technology": "Battery",
   "capacity_mw": 49.5,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Renfrewshire",
   "planning_ref": "25/0779/PP",
   "operator": "Bluestone Energy",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2025, still waiting for a decision",
    "who": "Renfrewshire Council",
    "evidence": {
     "submitted": "2025-09-18",
     "months_waiting": 10
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "South Clyde Energy Centre",
   "repd_ref_id": 1009,
   "technology": "EfW Incineration",
   "capacity_mw": 45.0,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2012-12-14",
   "refused": null,
   "planning_authority": "Glasgow City",
   "planning_ref": "12/01293/DC",
   "operator": "Fortum (formerly Peel Environmental)",
   "reason": {
    "reason": "gate2",
    "label": "Cleared the grid queue review, so it now has a firm connection date",
    "who": "the grid operator (NESO)",
    "evidence": {
     "project": "South Clyde Energy Centre",
     "gate2_outcome": "Cleared the grid queue review, so it now has a firm connection date"
    },
    "all_matches": [
     "gate2",
     "connection_date",
     "building"
    ]
   },
   "earliest": "2026",
   "tec": {
    "project": "South Clyde Energy Centre",
    "connection_date": "2026-06-30",
    "connection_year": 2026,
    "mw": 45.0,
    "stage": null,
    "who": "the grid operator (NESO) and SP Transmission",
    "gate2_outcome": "Cleared the grid queue review, so it now has a firm connection date",
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Glasgow Airport Solar Farm",
   "repd_ref_id": 10549,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 19.9,
   "homes_equivalent": 7200,
   "status": "Under Construction",
   "consented": "2023-04-06",
   "refused": null,
   "planning_authority": "Renfrewshire",
   "planning_ref": "22/0746/PP",
   "operator": "AGS Airports Limited",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "East Fulwood Greenock Road - Solar Farm",
   "repd_ref_id": 9946,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 14.3,
   "homes_equivalent": 5200,
   "status": "Awaiting Construction",
   "consented": "2023-01-24",
   "refused": null,
   "planning_authority": "Renfrewshire",
   "planning_ref": "22/0582/PP",
   "operator": "Springfield Limited / Aggreko",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-01-24",
     "years_since_consent": 3.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "S14000102",
  "S14000088",
  "S14000093"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}