Inverclyde and Renfrewshire West

MP: Martin McCluskey (Labour) Scotland Data to July 2026

Inverclyde and Renfrewshire West has 1.3 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 500 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,329 homes. There is also 24 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 388 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Auchentiber Road - Battery Energy Storage SystemApatura GPC 700 Limited Battery
700 MW
Cannot connect to the grid until 2029, 5 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission
Houston Solar PV Farm & Energy Storage FacilityThe Old Rectory Solar 27,000 homes
75 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Flatterton Farm, Flatterton Road - Battery StorageBig Battery (Flatterton Farm) Limited Battery
50 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.