Orkney and Shetland was paid £15m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.1 years. A further 333 MW of approved clean power (all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 291,000 homes. A 15 MW battery approved at Luggies Knowe, Hill Of Gremista in 2025 would store power that is currently wasted; it has not been built.

Ranks 12 of 650 for clean power approved and not built; 6 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Energy Isles Wind FarmEnergy Isles / Stratcraft Onshore wind 110,000 homes
126 MW
Cannot connect to the grid until 2032, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission
Shetland Battery Energy Storage SystemZenobe Energy Battery
70 MW
Under constructionWho can move it: the developer
Beaw Field Wind FarmPeel Wind Farms Onshore wind 52,000 homes
60 MW
Cannot connect to the grid until 2032, 15 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission