Orkney and Shetland
Orkney and Shetland was paid £16m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.2 years. A further 333 MW of approved clean power (all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 291,000 homes. A 15 MW battery approved at Luggies Knowe, Hill Of Gremista in 2025 would store power that is currently wasted; it has not been built.
Ranks 13 of 650 for clean power approved and not built; 5 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Energy Isles Wind FarmEnergy Isles & Stratcraft | Onshore wind | 126 MW110,000 homes | Cannot connect to the grid until 2032, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2032 · planning ref ECU00001844 |
| Shetland Battery Energy Storage SystemZenobe Energy | Battery | 70 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00004881 |
| Beaw Field Wind FarmPeel Wind Farms | Onshore wind | 60 MW52,000 homes | Cannot connect to the grid until 2032, 15 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2032 · planning ref EC00003121 |
| Neshion Energy Park - Wind FarmNeshion Energy Park | Onshore wind | 58 MW51,000 homes | Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006120 |
| Mossy HillPeel Wind Farms (Peel Energy) | Onshore wind | 47 MW41,000 homes | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2029 · planning ref 2018/186/PPF |
| Burgar Hill RepowerBurgar Hill Energy Limited (Thrive Renewables) | Onshore wind | 30 MW26,000 homes | Applied in 2026, still waiting for a decisionWho can move it: Orkney Islands Council · planning ref 26/148/TPPMAJ |
| Orkney’s Community Wind Farm Project - QanternessOrkney Islands Council | Onshore wind | 29 MW25,000 homes | Cannot connect to the grid until 2028, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 20/037/TPPMAJ |
| Orkney’s Community Wind Farm Project - HoyOrkney Islands Council | Onshore wind | 29 MW25,000 homes | Cannot connect to the grid until 2028, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 20/313/TPPMAJ |
| Orkney’s Community Wind Farm Project - FarayOrkney Islands Council | Onshore wind | 29 MW25,000 homes | Waiting 5.1 years for a planning decisionWho can move it: Orkney Islands Council · earliest connection 2030 · planning ref 21/240/TPPMAJ |
| Nitshill Wind Farm, Hundland HillNisthill Wind Farm Limited | Onshore wind | 26 MW23,000 homes | Waiting 3.9 years for a planning decisionWho can move it: Orkney Islands Council · planning ref 22/320/TPPMAJ |
| Neshion Energy Park - BESSNeshion Energy Park | Battery | 25 MW | Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006120 |
| Greentoft, Neven Point, Eday - Wind Turbines & BESSGreen Power (International) Limited | Onshore wind | 24 MW21,000 homes | Waiting 13 months for a planning decisionWho can move it: Orkney Islands Council · planning ref 25/203/TPPMAJ |
Plus 11 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Orkney and Shetland | 333 MW | 493 MW | £16m |
| Caithness, Sutherland and Easter Ross | 1,002 MW | 1,306 MW | £35m |
| Aberdeenshire North and Moray East | 216 MW | 122 MW | not visible |
| Gordon and Buchan | 107 MW | 187 MW | £130k |
Caithness, Sutherland and Easter Ross next door has 1,002 MW waiting, more than Orkney and Shetland's 333 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.