CONSTITUENCY BRIEFING · ENERGYMAP.APP

Aberdeenshire North and Moray East

MP: Seamus Logan (Scottish National Party) Scotland Data to July 2026

Aberdeenshire North and Moray East has 215 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 88,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,246 homes. There is also 121 MW of wind running here on the local network. If that gets switched off, no national record shows it. A 50 MW battery was refused planning here in 2025; while discharging it could have supplied about 175,000 homes.

Ranks 18 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Greystone, Blackhills - Battery Energy Storage SystePeterhead Flexpower Battery
500 MW
Waiting 1.1 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)
Netherton, Langside Road - Battery Energy Storage SyField Energy Battery
400 MW
Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects)
Flushing, Longside - Battery Energy Storage SystemHarmony Energy Storage Battery
400 MW
Waiting 1.1 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.