CONSTITUENCY BRIEFING · ENERGYMAP.APP

Caithness, Sutherland and Easter Ross

MP: Jamie Stone (Liberal Democrat) Scotland Data to July 2026 energymap.app

Caithness, Sutherland and Easter Ross was paid £36m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.2 years. A further 938 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 819,000 homes. A 300 MW battery approved at Philips Mains, Mey in 2026 would store power that is currently wasted; it has not been built.

Ranks 1 of 650 for clean power approved and not built; 2 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeApprovedWhy it is stuckEarliest
Titan Battery StorageGreen Switch Capital Limited Battery
500 MW
Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · Planning ref ECU00005199
Philips Mains, Mey - Battery Energy StorageAmpeak Energy Battery
300 MW
2026 Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · Planning ref ECU00004838
Spittal Mains, Spittal - Battery Energy Storage SystField Spittal Limited Battery
300 MW
Waiting 1.6 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · Planning ref ECU00005116
Upper Bighouse Biomass BoilersUpper Bighouse Farm Biomass (dedicated)
260 MW
Waiting 5.5 years for a planning decisionWho can move it: Highland Council · Planning ref 21/00334/FUL
Invershin Community Hall - Wind Farm & Battery StoraGarvary Wind Farm Limited Onshore wind 194,000 homes
222 MW
2025 Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · Planning ref ECU00003251
Strathy SouthScottish and Southern Energy (SSE) Onshore wind 182,000 homes
208 MW
2018 Cannot connect to the grid until 2027, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · Planning ref EC00003113 2027
Inveroykel Wind FarmRWE Renewables UK Swindon Limited Onshore wind 167,000 homes
191 MW
Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · Planning ref ECU00005210 2031
Achies - Battery Energy Storage SystemSun4net Limited Battery
162 MW
Waiting 1.2 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · Planning ref ECU00006111 2037

Plus 75 smaller projects — see the full seat page.

What building it would do here

Estimates from published per-MW factors — sources and dates in the method.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Caithness, Sutherland and Easter Ross 938 MW1,306 MW£36m
Inverness, Skye and West Ross-shire 453 MW1,272 MW£41m

Caithness, Sutherland and Easter Ross has more approved-and-waiting capacity than any of its neighbouring seats.

What to ask

WRITTEN PARLIAMENTARY QUESTION · DEPARTMENT FOR ENERGY SECURITY AND NET ZERO
To ask the Secretary of State for Energy Security and Net Zero, what steps she is taking to bring forward the grid connection date for Strathy South in Caithness, Sutherland and Easter Ross, which received planning permission in 2018 and holds a connection offer for 2027.
LETTER TO THE GRID OPERATOR (NESO) AND SSEN TRANSMISSION
I am writing about Strathy South in my constituency of Caithness, Sutherland and Easter Ross. The project already has planning permission, but cannot connect to the grid until 2027. Please set out what would be required to bring that date forward, whether the project has been considered for an earlier connection, and what my constituents can expect in the meantime.

Constituents can write to Jamie Stone via WriteToThem, or see what they have said about the grid in Parliament.

Story angles

1. Wind farms in Caithness, Sutherland and Easter Ross were paid £36m last year not to generate — enough to pay for every household here's electricity for about 1.2 years.
2. Approved in 2023, connecting in 2033: the wind onshore project in Caithness, Sutherland and Easter Ross that will wait 10 years for a wire.
3. Approved in 2018, connecting in 2027: the wind onshore project in Caithness, Sutherland and Easter Ross that will wait 9 years for a wire.

Numbers, CSVs and per-seat JSON are free to reuse with attribution to energymap.app. Method and caveats.

Sources. Switch-off payments: Elexon settlement data, 12 months to 31 Jul 2026. Planning: Renewable Energy Planning Database (DESNZ), July 2026. Connection dates: NESO Transmission Entry Capacity register. Bill impact: NESO balancing cost reporting. Households: ONS/NRS/NISRA census. MP: UK Parliament Members API.
How to check any of this. Every project above carries its planning application reference. Search that reference on the council's own planning register for the primary record, including the decision notice and, where a project was refused, the reasons. Statuses here come from the government's planning database (REPD, July 2026 edition), which records the status and date of a decision but not the reasons for it — so this briefing never states why something was refused.
Caveats for this seat. The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Generated 25 August 2026 · full method at energymap.app/method