Caithness, Sutherland and Easter Ross

MP: Jamie Stone (Liberal Democrat) Scotland Data to July 2026

Caithness, Sutherland and Easter Ross was paid £35m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.2 years. A further 1,002 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 868,000 homes. A 300 MW battery approved at Philips Mains, Mey in 2026 would store power that is currently wasted; it has not been built.

Ranks 2 of 650 for clean power approved and not built; 2 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Titan Battery StorageGreen Switch Capital Limited Battery 500 MW Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005199
Philips Mains, Mey - Battery Energy StorageAmpeak Energy Battery 300 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004838
Spittal Mains, Spittal - Battery Energy Storage SystemField Spittal Limited Battery 300 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005116
Upper Bighouse Biomass BoilersUpper Bighouse Farm Biomass (dedicated) 260 MW Waiting 5.5 years for a planning decisionWho can move it: Highland Council · planning ref 21/00334/FUL
Invershin Community Hall - Wind Farm & Battery StorageGarvary Wind Farm Limited Onshore wind 222 MW194,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003251
Strathy SouthScottish and Southern Energy (SSE) Onshore wind 208 MW182,000 homes Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2030 · planning ref EC00003113
Corriemoillie Quarry - Battery Energy StorageField Energy Battery 200 MW Waiting 20 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005155
Fyrish Battery Energy Storage SystemField Energy Battery 200 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005179
Achies - Battery Energy Storage SystemSun4net Limited Battery 162 MW Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00006111
Ballach Wind FarmEnergiekontor (UK) Limited Onshore wind 144 MW126,000 homes Cannot connect to the grid until 2037Who can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2037 · planning ref ECU00005219
Invercassley Wind Farm, Rosehall - Wind Farm & Battery StorageFred Olsen Renewables Limited Onshore wind 144 MW126,000 homes Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006064
Inveroykel Wind FarmRWE Renewables UK Swindon Limited Onshore wind 132 MW115,000 homes Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2031 · planning ref ECU00005210

Plus 87 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Caithness, Sutherland and Easter Ross 1,002 MW1,306 MW£35m
Inverness, Skye and West Ross-shire 453 MW1,272 MW£46m

Caithness, Sutherland and Easter Ross has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.