No.12 OF 650 · APPROVED, NOT BUILT MP: Mr Alistair Carmichael (Liberal Democrat) Scotland

Orkney and Shetland

Orkney and Shetland was paid £15m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.1 years. A further 333 MW of approved clean power (all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 291,000 homes. A 15 MW battery approved at Luggies Knowe, Hill Of Gremista in 2025 would store power that is currently wasted; it has not been built.

£15m
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for about 1.1 years.
Elexon balancing data, 12 months to 31 Jul 2026 · No.6 of 19 seats with visible switch-offs · how we worked this out
333 MW
of clean power — all onshore wind — approved and still not built, enough to supply a year's electricity to 291,000 homes — 14 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 0.7× the renewable capacity actually running here.
11 projects · planning database (REPD), July 2026 · how we worked this out
£1.9m
is what the grid gap costs this constituency's 21,204 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 11 waiting projects · years since approval
Beaw Field Wind Farm 60 MW
8.7 YRS
Hesta Head Wind Farm 20 MW
7.3 YRS
Costa Head Wind Farm 16 MW
7.3 YRS
Mossy Hill 47 MW
7.2 YRS
Orkney’s Community Wind Farm Project - Qanterness 29 MW
4.6 YRS
Orkney’s Community Wind Farm Project - Hoy 29 MW
4.6 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Energy Isles Wind FarmWind Onshore110,000 homes126.0 MW2023-102.8 yrs
Beaw Field Wind FarmWind Onshore52,000 homes59.5 MW2017-118.7 yrs
Mossy HillWind Onshore41,000 homes46.8 MW2019-057.2 yrs
Orkney’s Community Wind Farm Project - QanternessWind Onshore25,000 homes28.8 MW2021-124.6 yrs
Orkney’s Community Wind Farm Project - HoyWind Onshore25,000 homes28.8 MW2021-124.6 yrs
Hesta Head Wind FarmWind Onshore18,000 homes20.4 MW2019-047.3 yrs
Costa Head Wind FarmWind Onshore14,000 homes16.3 MW2019-047.3 yrs
AklaWind Onshore2,400 homes2.7 MW2012-1213.6 yrs
North Hoo FieldsWind Onshore2,000 homes2.3 MW2024-072.1 yrs
Hammer, Skelwick - Wind TurbineWind Onshore400 homes0.5 MW2023-122.7 yrs
Ludenhill, Lochside Road - Wind TurbineWind Onshore400 homes0.5 MW2024-032.4 yrs

Plus 4 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Shetland Battery Energy Storage System70 MWbeing built 2024could supply ≈245,000 homes
Luggies Knowe, Hill Of Gremista - Wind Turbines & Battery Storage15 MWapproved, not built 2025could supply ≈52,000 homes
Greentoft, Neven Point, Eday - Wind Turbines & BESS10 MWcould supply ≈35,000 homes

Wind farms paid to switch off

12 months to 31 Jul 2026 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Viking Wind Farm£15ma year of 511,000 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Mr Alistair Carmichael said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)