CONSTITUENCY BRIEFING · ENERGYMAP.APP

Cramlington and Killingworth

MP: Emma Foody (Labour (Co-op)) England Data to July 2026

Cramlington and Killingworth has 31 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 11,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,055 homes.

Ranks 174 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Low Horton - Battery Energy Storage SystemBluefield Renewable Developments Limited Battery
50 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Backworth Lane, Backworth - Solar FarmNorthumberland Estates Solar 10,000 homes
28 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Seghill Household Waste Recovery Centre -Solar PanelSuez Recycling and Recovery UK Limited Solar 2,100 homes
5.8 MW
Applied in 2025, still waiting for a decisionWho can move it: Northumberland Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.