CONSTITUENCY BRIEFING · ENERGYMAP.APP
Newcastle upon Tyne North
Newcastle upon Tyne North has 2.7 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 45,290 homes.
Ranks 314 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Benton Lane, Quorum Business Park - Solar PanelsShelborn Asset Management | Solar | 8 MW2,900 homes | Applied in 2026, still waiting for a decisionWho can move it: North Tyneside Council · planning ref 25/01018/FULM |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Newcastle upon Tyne North | 2.7 MW | 0 MW | not visible |
| Hexham | 23 MW | 56 MW | not visible |
| Newcastle upon Tyne Central and West | 3.7 MW | 0 MW | not visible |
| Newcastle upon Tyne East and Wallsend | 2.3 MW | 0 MW | not visible |
| Cramlington and Killingworth | 31 MW | 4 MW | not visible |
Cramlington and Killingworth next door has 31 MW waiting, more than Newcastle upon Tyne North's 2.7 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call