CONSTITUENCY BRIEFING · ENERGYMAP.APP

Blyth and Ashington

MP: Ian Lavery (Labour) England Data to July 2026

Blyth and Ashington has 150 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 54,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.3m across the constituency's 46,755 homes. There is also 29 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 35 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
High Brockland Farm, Brock Lane - Battery Energy Storage SystemBluefield Renewable Developments Limited Battery 70 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/01726/FUL
Burnt House Farm, Nedderton Village - Battery Energy Storage SystemBluefield Renewable Developments Limited Battery 50 MW Waiting 16 months for a planning decisionWho can move it: Northumberland Council · planning ref 25/01144/FUL
Low Horton Farm - Solar FarmBluefield Renewable Developments Limited Solar 50 MW18,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01153/RENE
Broadway House Farm Solar FarmBluefield Renewable Developments Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/02205/RENE
Burnt House Farm - Solar FarmBluefield Renewable Developments Limited Solar 50 MW18,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01082/RENE
West Sleekburn - Battery Storage CompoundEnviromena Asset Management UK Limited Battery 30 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01725/FUL

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Blyth and Ashington 150 MW32 MWnot visible
Hexham 23 MW56 MWnot visible
Cramlington and Killingworth 31 MW4 MWnot visible
North Northumberland 13 MW187 MWnot visible

Blyth and Ashington has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call