Blyth and Ashington has 150 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 54,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.3m across the constituency's 46,755 homes. There is also 29 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 35 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
High Brockland Farm, Brock Lane - Battery Energy StoBluefield Renewable Developments Limited Battery
70 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Burnt House Farm, Nedderton Village - Battery EnergyBluefield Renewable Developments Limited Battery
50 MW
Waiting 1.3 years for a planning decisionWho can move it: Northumberland Council
Broadway House Farm Solar FarmBluefield Renewable Developments Limited Solar 18,000 homes
50 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company