MP: Joe Morris (Labour) England Data to July 2026

Hexham has 23 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 8,200 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 41,294 homes. There is also 50 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 189 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Newburn BESS - Battery Energy Storage SystemFig Power Battery
90 MW
Waiting 2.2 years for a planning decisionWho can move it: Newcastle upon Tyne Council
Fourstones -Battery Energy StorageMespil Solar Energy Battery
60 MW
Applied in 2025, still waiting for a decisionWho can move it: Northumberland Council
Fourstones - Solar ParkMespil Solar Energy Solar 18,000 homes
50 MW
Applied in 2025, still waiting for a decisionWho can move it: Northumberland Council