CONSTITUENCY BRIEFING · ENERGYMAP.APP

North Ayrshire and Arran

MP: Irene Campbell (Labour) Scotland Data to July 2026

North Ayrshire and Arran has 74 MW of clean power (mostly solar) approved and still not built: enough to supply a year's electricity to 33,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,516 homes. There is also 100 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 92 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Hunterston Grid Services Complex - Energy Storage FaAmp Energy Battery
400 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company
Flemyland Battery StorageFlemyland Battery Storage Limited Battery
100 MW
Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO)
High Boydstone Farm - Battery Energy Storage FacilitNew Energy Partnership Battery
100 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.