Central Ayrshire

MP: Alan Gemmell (Labour) Scotland Data to July 2026

Central Ayrshire has 51 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 20,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 41,117 homes.

Ranks 129 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Camsiscan Farm, Craigie - Battery Energy Storage SysNoriker Power Limited Battery
350 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Belston Battery StorageKX Alpha Ltd Battery
150 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Kilwinning Battery StorageApatura Battery
100 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company