CONSTITUENCY BRIEFING · ENERGYMAP.APP

Na h-Eileanan an Iar

MP: Torcuil Crichton (Labour) Scotland Data to July 2026

Na h-Eileanan an Iar has 254 MW of clean power (all onshore wind) approved and still not built: enough to supply a year's electricity to 222,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £1.2m across the constituency's 12,717 homes. There is also 38 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 14 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Stornoway Wind Farm (second resubmission)EDF Renewables UK / ESB Onshore wind 196 MW171,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00001850
Sandwick East Community Wind FarmAquatera Onshore wind 50 MW44,000 homes Waiting 7.3 years for a planning decisionWho can move it: Na h-Eileanan Siar Council · planning ref 9/00189/PPDM
Druim Leathann WindfarmBaywa R.E. UK Limited Onshore wind 48 MW42,000 homes Cannot connect to the grid until 2027, 5 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2027 · planning ref 18/00216/PPDM
Battery Point, Newton Street - Battery Energy Storage ParkPoint & Sandwick Trust Battery 25 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00155/PPDM
Beinn Thulabaigh Wind TurbineKnock and Swordale Community Company Onshore wind 5 MW4,400 homes Approved 6 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 19/00209/PPW

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Na h-Eileanan an Iar 254 MW38 MWnot visible
Caithness, Sutherland and Easter Ross 938 MW1,306 MW£36m
Inverness, Skye and West Ross-shire 453 MW1,272 MW£41m
Moray West, Nairn and Strathspey 642 MW525 MW£17m

Caithness, Sutherland and Easter Ross next door has 938 MW waiting, more than Na h-Eileanan an Iar's 254 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.