Moray West, Nairn and Strathspey

MP: Graham Leadbitter (Scottish National Party) Scotland Data to July 2026

Moray West, Nairn and Strathspey was paid £17m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 213 days. A further 642 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 523,000 homes. A 50 MW battery approved at Clash Gour in 2022 would store power that is currently wasted; it has not been built.

Ranks 4 of 650 for clean power approved and not built; 4 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Dorenell Extension Wind FarmGalileo Onshore wind 417,000 homes
477 MW
Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects)
Clash GourEDF Energy Renewables/ Force 9 Onshore wind 197,000 homes
225 MW
Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company
Glenshero Wind FarmRES/ SIMEC Onshore wind 147,000 homes
168 MW
Refused by the Scottish Government (it decides big energy projects) in 2022Who can move it: the Scottish Government (it decides big energy projects)