CONSTITUENCY BRIEFING · ENERGYMAP.APP

Angus and Perthshire Glens

MP: Dave Doogan (Scottish National Party) Scotland Data to July 2026

Angus and Perthshire Glens was paid £5.2m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 63 days. A further 143 MW of approved clean power (all solar) is still waiting to be built here: enough to supply a year's electricity to 52,000 homes. A 900 MW battery approved at Haughend Farm - Alyth Battery Energy Storage System in 2024 would store power that is currently wasted; it has not been built.

Ranks 40 of 650 for clean power approved and not built; 10 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Haughend Farm - Alyth Battery Energy Storage SystemEcoDev Group Limited Battery 900 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004631
Stracathro - Battery Energy Storage SystemOpdenergy UK 8 Limited Battery 249 MW Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2032 · planning ref ECU00004807
Meall Dearg Wind Farm - Wind FarmEnergiekontor (UK) Limited Onshore wind 147 MW129,000 homes Cannot connect to the grid until 2037Who can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2037 · planning ref ECU00006049
Balnuith Farm, Tealing - Battery StorageApatura Battery 100 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004887
Hallyburton - Battery StorageBalance Power Projects Limited Battery 100 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004931
North Logiealmond Wind FarmMuirhall Energy Limited Onshore wind 94 MW82,000 homes Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006004
Stirling Battery and Solar Energy ParkEcoDev Group Limited Solar 60 MW22,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005014
Craigo Glenskinno - Solar and Battery FarmBritish Solar Renewables Solar 60 MW22,000 homes Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006104
Craigo Glenskinno - Solar and Battery FarmBritish Solar Renewables Battery 60 MW Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006104
Stirling Battery and Solar Energy ParkEcoDev Group Limited Battery 50 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005014
Balwyllo Farm, Dun - Energy Storage FacilityWhirlwind Energy Storage Limited Battery 50 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00754/FULM
Whitehills Energy Storage FacilityGigabox Developments Limited & Whirlwind Renewables Battery 50 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 21/00534/FULM

Plus 29 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Angus and Perthshire Glens 143 MW345 MW£5.2m
Arbroath and Broughty Ferry 96 MW31 MWnot visible
Argyll, Bute and South Lochaber 446 MW460 MW£1.9m
Stirling and Strathallan 52 MW193 MWnot visible
Perth and Kinross-shire 43 MW44 MWnot visible
Dundee Central 52 MW0 MWnot visible

Argyll, Bute and South Lochaber next door has 446 MW waiting, more than Angus and Perthshire Glens's 143 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.