No.4 OF 650 · APPROVED, NOT BUILT MP: Graham Leadbitter (Scottish National Party) Scotland

Moray West, Nairn and Strathspey

Moray West, Nairn and Strathspey was paid £17m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 213 days. A further 642 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 523,000 homes. A 50 MW battery approved at Clash Gour in 2022 would store power that is currently wasted; it has not been built.

£17m
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for 213 days.
Elexon balancing data, 12 months to 31 Jul 2026 · No.4 of 19 seats with visible switch-offs · how we worked this out
642 MW
of clean power — almost all onshore wind — approved and still not built, enough to supply a year's electricity to 523,000 homes — 12 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 1.2× the renewable capacity actually running here.
10 projects · 568 MW onshore wind, 74 MW solar · planning database (REPD), July 2026 · how we worked this out
£4.2m
is what the grid gap costs this constituency's 45,493 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 10 waiting projects · years since approval
Speyslaw Solar Farm 20 MW
9.0 YRS
Milltown Airfield (Speyslaw) 50 MW
8.2 YRS
Pauls Hill 2 28 MW
5.6 YRS
Berry Burn Wind Farm (extension) 38 MW
4.6 YRS
Clash Gour 225 MW
4.3 YRS
Garbet Windfarm - Wind Farm & Storage facility 46 MW
3.9 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Clash GourWind Onshore197,000 homes225.0 MW2022-044.3 yrs
Rothes Wind Farm IIIWind Onshore115,000 homes132.0 MW2022-103.8 yrs
Cairn Duhie Wind FarmWind Onshore59,000 homes67.2 MW2024-022.5 yrs
Milltown Airfield (Speyslaw)Solar Photovoltaics18,000 homes50.0 MW2018-058.2 yrs
Garbet Windfarm - Wind Farm & Storage facilityWind Onshore40,000 homes46.2 MW2022-093.9 yrs
Berry Burn Wind Farm (extension)Wind Onshore33,000 homes37.8 MW2021-124.6 yrs
Tom Na Clach - Wind Farm ExtensionWind Onshore28,000 homes31.5 MW2024-052.2 yrs
Pauls Hill 2Wind Onshore24,000 homes28.0 MW2020-125.6 yrs
Speyslaw Solar FarmSolar Photovoltaics7,300 homes20.0 MW2017-089.0 yrs
Craigellachie Biomass CHP Plant, Craigellachie- Solar FarmSolar Photovoltaics1,500 homes4.0 MW2024-012.6 yrs

Plus 3 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Clash Gour50 MWapproved, not built 2022could supply ≈175,000 homes
Ourack50 MWapproved, not built 2025could supply ≈175,000 homes
Househill House, Househill - Battery Storage50 MWapproved, not built 2023could supply ≈175,000 homes
Loanhead Farm - Battery Energy Storage System50 MWcould supply ≈175,000 homes
Grigorhill Cottage, Grigorhill - Battery Energy Storage50 MWapproved, not built 2026could supply ≈175,000 homes
Blackpark Energy Storage30 MWapproved, not built 2020could supply ≈105,000 homes
Blackpark House - Battery Storage30 MWapproved, not built 2025could supply ≈105,000 homes
Bishopmill - Battery Energy Storage30 MWapproved, not built 2023could supply ≈105,000 homes
Kellas Wind Farm30 MWapproved, not built 2026could supply ≈105,000 homes
Craig Watch - Wind Farm & Battery Storage27 MWcould supply ≈96,000 homes
Dorenell Extension Wind Farm20 MWcould supply ≈70,000 homes
Blackhills Wind Farm20 MWcould supply ≈70,000 homes

Wind farms paid to switch off

12 months to 31 Jul 2026 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Dorenell Wind Farm (Previously Site A and B Scaut Hill)£13ma year of 112,000 homes' electricitymedium
Paul's Hill and Extension£2.0ma year of 8,900 homes' electricityhigh
Rothes Wind (Cairn Uish)£1.2ma year of 5,600 homes' electricitymedium
Rothes Wind Farm (Extension) (II)£1.0ma year of 4,600 homes' electricitymedium

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Graham Leadbitter said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)