CONSTITUENCY BRIEFING · ENERGYMAP.APP

Horsham

MP: John Milne (Liberal Democrat) England Data to July 2026

Horsham has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 19,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,452 homes. A 57 MW battery was refused planning here in 2024; while discharging it could have supplied about 200,000 homes.

Ranks 125 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Great Oak Energy HubClearstone Energy Limited Battery
400 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Bolney - Battery StorageElements Green Battery
200 MW
Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO)
Kent Street, Cowfold - Battery Energy Storage SystemEnso Energy / Bolney Green Energy Hub Battery
57 MW
Refused by Horsham Council in 2024Who can move it: Horsham Council