CONSTITUENCY BRIEFING · ENERGYMAP.APP
Arundel and South Downs
Arundel and South Downs has 21 MW of renewables running, enough for 7,700 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,254 homes.
Ranks 569 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Boxgrove Common, Tinwood Lane - Battery Energy StoraNet Zero Fifteen Limited | Battery | 70 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Horsham Road - Solar Farm & Battery StorageBolney Green Limited | Solar | 18,000 homes 50 MW |
Waiting 4.5 years for a planning decisionWho can move it: Horsham Council |
| Wisborough Green - Solar Photovoltaic PanelsRenewable Connections Developments Limited | Solar | 7,300 homes 20 MW |
Waiting 1.4 years for a planning decisionWho can move it: Chichester Council |
What else is in the briefing
- All 4 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Arundel and South Downs compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
No account needed for any of this:
the full seat page with every figure,
the method and sources,
and this constituency's raw data.
The account covers the packaged briefing only.