CONSTITUENCY BRIEFING · ENERGYMAP.APP

Godalming and Ash

MP: Sir Jeremy Hunt (Conservative) England Data to July 2026

Godalming and Ash has 1 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 400 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,040 homes.

Ranks 420 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Guildford Road Battery Storage FacilityConrad Energy (Developments) Limited Battery
14 MW
Waiting 5.7 years for a planning decisionWho can move it: Waverley Council
University of Surrey, Blackwell Farm - Solar FarmSSE Enterprise Contracting Solar 4,400 homes
12 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Tuesley Farm, Tuesley Lane - Solar ArrayHall Hunter Partnership Solar 400 homes
1 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company