CONSTITUENCY BRIEFING · ENERGYMAP.APP

North Durham

MP: Luke Akehurst (Labour) England Data to July 2026

North Durham has 28 MW of renewables running, enough for 21,000 homes over a year, and nothing large waiting in the planning queue. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,950 homes. There is also 21 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 437 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Edge Lane, Maiden Law - Solar Farm & Battery StorageLightsource BP Solar 18,000 homes
50 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Edge Lane, Maiden Law - Solar Farm & Battery StorageLightsource BP Battery
45 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Maiden, Annfield Plain - Energy StorageStephenson Mohl Development Battery
38 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.