Carlisle has 70 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 25,000 homes. No wind farm here is paid to switch off. Almost every pound of that money goes to wind farms in Scotland, where there is not enough wire capacity to carry the power south. The cost is shared across every bill in Britain, so households here pay too: about £92 a year per household, £4.4m across the constituency's 47,449 homes. There is also 44 MW of wind running here on the local network. If that gets switched off, no national record shows it. A 340 MW battery was refused planning here in 2026; while discharging it could have supplied about 1,191,000 homes.

Ranks 96 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Low Harker Farm, Low Harker - Battery Storage FaciliZenobe Energy Limited Battery
400 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company
Blackdyke Farm, Blackford - Battery StorageInnova Renewables Battery
400 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Harker Moss - Battery Energy Storage SystemESB (Harker) Limited Battery
360 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company