CONSTITUENCY BRIEFING · ENERGYMAP.APP

Grantham and Bourne

MP: Gareth Davies (Conservative) England Data to July 2026

Grantham and Bourne has 151 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 55,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,089 homes.

Ranks 32 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Canners Lane Energy Park, High Dike - Battery EnergyNatPower UK Battery
1,000 MW
Applied in 2025, still waiting for a decisionWho can move it: North Kesteven Council
Heckington Fen Solar ParkEcotricity Limited Solar 182,000 homes
500 MW
Cannot connect to the grid until 2028, 3 years after it was approvedWho can move it: the grid operator (NESO) and National Grid
Little Hale Drove, Little Hale Fen - Battery StorageRoot-Power (South) Limited Battery
99 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.