Boston and Skegness
Boston and Skegness has 125 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 46,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.6m across the constituency's 50,378 homes. There is also 29 MW of wind running here on the local network. If that gets switched off, no national record shows it.
Ranks 45 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Bicker Fen Bess, Vicarage Drove - Battery StorageFRV TH Powertek Limited | Battery | 400 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Boston Alternative Energy Facility (BAEF)Alternative Use Boston Projects | EfW Incineration | 102 MW |
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company |
| Bicker Drove - Battery Energy Storage SystemNet Zero Twenty Two Limited | Battery | 100 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 12 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Boston and Skegness compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call