Dumfries and Galloway

MP: John Cooper (Conservative) Scotland Data to July 2026

Dumfries and Galloway was paid £11m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 132 days. A further 560 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 488,000 homes. A 40 MW battery approved at Kellwood Road in 2025 would store power that is currently wasted; it has not been built.

Ranks 7 of 650 for clean power approved and not built; 7 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Blair Hill Wind FarmRES Limited Onshore wind 127,000 homes
145 MW
Waiting 1.4 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)
Mid Moile Wind FarmEnergieKontor UK Limited Onshore wind 87,000 homes
99 MW
Cannot connect to the grid until 2031, 6 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission
Quantans Hill Wind FarmVattenfall Wind Power Limited Onshore wind 84,000 homes
96 MW
Waiting 3.5 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.