CONSTITUENCY BRIEFING · ENERGYMAP.APP

Ayr, Carrick and Cumnock

MP: Elaine Stewart (Labour) Scotland Data to July 2026

Ayr, Carrick and Cumnock was paid £18m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 233 days. A further 654 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 571,000 homes. A 500 MW battery approved at Braston New Energy in 2025 would store power that is currently wasted; it has not been built. A 25 MW battery was refused planning here in 2023; while discharging it could have supplied about 88,000 homes.

Ranks 3 of 650 for clean power approved and not built; 3 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Braston New EnergyNew Energy Partnership Battery
500 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
North Kyle Energy ProjectBrockwell Energy Onshore wind 180,000 homes
206 MW
Under constructionWho can move it: the developer
Lethans Wind FarmOnPath Energy Limited Onshore wind 92,000 homes
106 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.