Waveney Valley
Waveney Valley has 59 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 22,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.6m across the constituency's 39,383 homes.
Ranks 109 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Red House Farm, Old Norwich Road - Battery Energy StThe Surrey Research Park | Battery | 520 MW |
Waiting 1.1 years for a planning decisionWho can move it: Mid Suffolk Council |
| Market Lane And Carr Lane, Great Moulton - Battery EField Long Stratton Limited | Battery | 400 MW |
Waiting 1.2 years for a planning decisionWho can move it: South Norfolk Council |
| Yaxley, Eye Airfield Industrial Estate - Battery StoField Yaxley Limited | Battery | 200 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 16 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Waveney Valley compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting