Doncaster North
Doncaster North has 3.8 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,487 homes.
Ranks 278 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Thorpe Marsh Power Station - Battery Energy StorageWest Burton Energy | Battery | 1,450 MW |
Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) |
| Thorpe Marsh Power Station, Marsh Lane - Battery EneWest Burton Energy / Banks Group | Battery | 1,400 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| The Balk, Almholme - Energy Storage SystemInnova Renewables | Battery | 1,025 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 13 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Doncaster North compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call