North West Norfolk
North West Norfolk has 166 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 61,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,613 homes. There is also 24 MW of wind running here on the local network. If that gets switched off, no national record shows it.
Ranks 27 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Lapwing Fen 2 - Battery Storage PlantTribus Clean Energy | Battery | 250 MW |
Under constructionWho can move it: the developer |
| Walsoken, Burrettgate Road - Battery Storage FacilitWalsoken Limited | Battery | 200 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Walpole Bank - Battery Energy Storage FacilityField Devco Limited | Battery | 100 MW |
Waiting 3.7 years for a planning decisionWho can move it: King's Lynn and West Norfolk Council |
What else is in the briefing
- All 17 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How North West Norfolk compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call