North East Cambridgeshire has 2.9 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,100 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,083 homes. There is also 133 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 300 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Medworth EfWMVV Environment EfW Incineration
58 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company
Treading Bank Solar FarmRenewable Connections Solar 18,000 homes
50 MW
Refused by Fenland Council in 2025Who can move it: Fenland Council
West Fen Farm, Whitemoor Road - Solar FarmPathfinder Clean Energy UK Dev Limited Solar 18,000 homes
50 MW
Waiting 1.2 years for a planning decisionWho can move it: Fenland Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.