North West Essex has 623 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 226,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,575 homes.

Ranks 5 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeApprovedWhy it is stuckEarliest
LongfieldLongfield Solar Energy Farm Limited (part of E Solar 182,000 homes
500 MW
2023 Cannot connect to the grid until 2028, 5 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · Planning ref EN010118 2028
Berden Hall Solar FarmBritish Solar Renewables Solar 20,000 homes
56 MW
2024 Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · Planning ref UTT/22/2046/PINS
Maggots End Road, Berden - Solar Farm & Battery StorLow Carbon Limited Solar 18,000 homes
50 MW
Refused by Uttlesford Council in 2026Who can move it: Uttlesford Council · Planning ref UTT/25/1224/FUL
Thaxted - Solar farmLow Carbon Limited Solar 15,000 homes
40 MW
2023 Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · Planning ref UTT/21/1833/FUL
Parsonage Farm - Solar PV Farm & Battery StorageTrilogy Logistics REIT Limited Solar 11,000 homes
30 MW
2026 Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · Planning ref UTT/25/1742/FUL
Wickham Hall Estate Solar Photovoltaic FarmEndurance Energy Wickham Hall Limited Solar 7,300 homes
20 MW
2024 Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · Planning ref UTT/24/1417/PINS
Stanstead Solar ProjectManchester Airport Group Plc Solar 5,200 homes
14 MW
2022 Under constructionWho can move it: the developer · Planning ref S62A/22/0000004 2027 (in construction)
Merks Hill Farm, Braintree Road - Solar FarmSky UK Development Limited Solar 4,400 homes
12 MW
Waiting 1.2 years for a planning decisionWho can move it: Uttlesford Council · Planning ref UTT/25/1374/FUL

Plus 1 smaller projects — see the full seat page.

What building it would do here

Estimates from published per-MW factors — sources and dates in the method.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
North West Essex 623 MW68 MWnot visible
Brentwood and Ongar 1 MW50 MWnot visible
Maldon 139 MW63 MWnot visible
Chelmsford 0.2 MW0 MWnot visible
Harlow 56 MW0 MWnot visible
Witham 24 MW193 MWnot visible

North West Essex has more approved-and-waiting capacity than any of its neighbouring seats.

What to ask

WRITTEN PARLIAMENTARY QUESTION · DEPARTMENT FOR ENERGY SECURITY AND NET ZERO
To ask the Secretary of State for Energy Security and Net Zero, what steps she is taking to bring forward the grid connection date for Longfield in North West Essex, which received planning permission in 2023 and holds a connection offer for 2028.
LETTER TO THE GRID OPERATOR (NESO) AND NATIONAL GRID
I am writing about Longfield in my constituency of North West Essex. The project already has planning permission, but cannot connect to the grid until 2028. Please set out what would be required to bring that date forward, whether the project has been considered for an earlier connection, and what my constituents can expect in the meantime.

Constituents can write to Mrs Kemi Badenoch via WriteToThem, or see what they have said about the grid in Parliament.

Story angles

1. North West Essex has 623 MW of approved clean power waiting to be built — 9.1 times what is actually running here.
2. The clean power approved but unbuilt in North West Essex would pay an estimated £606k a year into local community funds if it were built.
3. Every household in North West Essex pays about £92 a year for a grid bottleneck most of them have never heard of — £3.9m across the constituency.

Numbers, CSVs and per-seat JSON are free to reuse with attribution to energymap.app. Method and caveats.

Sources. Switch-off payments: Elexon settlement data, 12 months to 31 Jul 2026. Planning: Renewable Energy Planning Database (DESNZ), July 2026. Connection dates: NESO Transmission Entry Capacity register. Bill impact: NESO balancing cost reporting. Households: ONS/NRS/NISRA census. MP: UK Parliament Members API.
How to check any of this. Every project above carries its planning application reference. Search that reference on the council's own planning register for the primary record, including the decision notice and, where a project was refused, the reasons. Statuses here come from the government's planning database (REPD, July 2026 edition), which records the status and date of a decision but not the reasons for it — so this briefing never states why something was refused.
Caveats for this seat. Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Generated 25 August 2026 · full method at energymap.app/method