Maldon
Maldon has 139 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 50,000 homes. No wind farm here is paid to switch off. Almost every pound of that money goes to wind farms in Scotland, where there is not enough wire capacity to carry the power south. The cost is shared across every bill in Britain, so households here pay too: about £92 a year per household, £3.8m across the constituency's 41,803 homes. There is also 58 MW of wind running here on the local network. If that gets switched off, no national record shows it. A 100 MW battery was refused planning here in 2022; while discharging it could have supplied about 350,000 homes.
Ranks 38 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Battlesbridge Bypass, Rettendon - Battery StoragePelagic Energy | Battery | 100 MW |
Refused by Chelmsford Council in 2022Who can move it: Chelmsford Council |
| Southlands Solar Farm & Battery StorageEnso Green Holdings Limited / Cero Generation | Battery | 57 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Canon Barns Road - Solar Photovoltaic Arrays & BatteLow Carbon Solar Park 5 Limited | Solar | 18,000 homes 50 MW |
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 12 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Maldon compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call