CONSTITUENCY BRIEFING · ENERGYMAP.APP

Harlow

MP: Chris Vince (Labour (Co-op)) England Data to July 2026

Harlow has 56 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 20,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 45,079 homes.

Ranks 111 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
East End Solar FarmLow Carbon Solar Park 18 Solar 18,000 homes
50 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company
Poundland Distribution Centre - Solar Photovoltaic SStandard Life Assurance Limited Solar 500 homes
1.5 MW
Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.