CONSTITUENCY BRIEFING · ENERGYMAP.APP

Newark

MP: Robert Jenrick (Reform UK) England Data to July 2026

Newark has 295 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 107,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,490 homes.

Ranks 13 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Great North Road Solar ParkElements Green Solar 290,000 homes
800 MW
Waiting 1.1 years for a planning decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects)
One Earth Solar FarmOrsted UK Limited / PS Renewables Solar 269,000 homes
740 MW
Cannot connect to the grid until 2029, 3 years after it was approvedWho can move it: the grid operator (NESO) and National Grid
Torksey Ferry Road, Rampton - Battery Energy StorageTribus Clean Energy Limited Battery
500 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.