CONSTITUENCY BRIEFING · ENERGYMAP.APP

Jarrow and Gateshead East

MP: Kate Osborne (Labour) England Data to July 2026

Jarrow and Gateshead East has 5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,800 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,695 homes.

Ranks 263 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Church Bank - Battery Storage SystemAMG Energy Battery
100 MW
Applied in 2025, still waiting for a decisionWho can move it: South Tyneside Council
West Boldon Substation - Battery Energy StorageWhirlwind Energy Storage Limited Battery
60 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
NCL1, Follingsby Lane - Solar PanelsZestec Asset Management Solar 1,400 homes
3.9 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.