No.268 of 650 · approved, not built MP: Kate Osborne (Labour) England

Jarrow and Gateshead East

Jarrow and Gateshead East has 5.4 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 2,000 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £4.9m across the constituency's 42,695 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
5.4 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 2,000 homes. Approved at least two years ago; waiting on the grid, not on planning.
4 projects · planning database (REPD), July 2026 · how we worked this out
£4.9m
is what the grid gap costs this constituency's 42,695 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

4 of 4 waiting projects · years since approval
Neilson Road - Solar Photovoltaic Array 0.9 MW
4.9 YRS
Robert Duncan Timber Limited, Green Lane - Solar Panels 0.2 MW
3.8 YRS
NCL1, Follingsby Lane - Solar Panels 3.9 MW
3.6 YRS
Simonside Industrial Unit, Shaftesbury Avenue - Solar Panels 0.4 MW
2.1 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
NCL1, Follingsby Lane - Solar PanelsNcl1 Follingsby LaneSolar Photovoltaics1,400 homes3.9 MW2023-043.6 yrs
Neilson Road - Solar Photovoltaic ArrayGateshead International Stadium Neilson Road, GatesheadSolar Photovoltaics300 homes0.9 MW2021-124.9 yrs
Simonside Industrial Unit, Shaftesbury Avenue - Solar PanelsFormer Biffa Unit Simonside Industrial Unit Shaftesbury AvenueSolar Photovoltaics100 homes0.4 MW2024-102.1 yrs
Robert Duncan Timber Limited, Green Lane - Solar PanelsRobert Duncan Timber Limited, Green Lane, FellingSolar Photovoltaics100 homes0.2 MW2023-013.8 yrs

Plus 5 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Church Bank - Battery Storage System100 MWcould supply ≈350,000 homes
West Boldon Substation - Battery Energy Storage60 MWapproved, not built 2024could supply ≈210,000 homes
Port of Tyne35 MWoperatingcould supply ≈123,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Kate Osborne said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)