CONSTITUENCY BRIEFING · ENERGYMAP.APP

Bassetlaw

MP: Jo White (Labour) England Data to July 2026

Bassetlaw has 114 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 41,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,676 homes.

Ranks 53 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Elkesley Southbound, Elkesley - Battery Energy StoraMespil Solar Energy Battery
480 MW
Waiting 1.2 years for a planning decisionWho can move it: Bassetlaw Council
Gainsborough Road, Saundby - Battery Storage FacilitEnso Energy / Cero Generation Battery
120 MW
Under constructionWho can move it: the developer
Gainsborough Road, Saundby - Solar FarmEnso Energy / Cero Generation Solar 28,000 homes
78 MW
Under constructionWho can move it: the developer

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.