Bassetlaw
Bassetlaw has 114 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 41,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,676 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Gainsborough Road, Saundby - Solar Farm | Solar Photovoltaics | 28,000 homes | 78.0 MW | 2022-07 | 4.1 yrs |
| Rayton Farm Lane - Solar Farm | Solar Photovoltaics | 12,000 homes | 34.0 MW | 2024-03 | 2.4 yrs |
| Schutz UK Limited, Claylands Avenue - Solar Panels | Solar Photovoltaics | 600 homes | 1.7 MW | 2023-07 | 3.0 yrs |
| Misterton PSD, Stockwith Road - Solar Panels | Solar Photovoltaics | 200 homes | 0.4 MW | 2024-02 | 2.4 yrs |
| Bridge Street - Solar Pv System | Solar Photovoltaics | 100 homes | 0.2 MW | 2024-06 | 2.1 yrs |
Plus 2 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Elkesley Southbound, Elkesley - Battery Energy Storage System | 480 MW | in planning | could supply ≈1,682,000 homes |
| Gainsborough Road, Saundby - Battery Storage Facility | 120 MW | being built 2022 | could supply ≈420,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →