Stroud
Stroud has 4 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 41,920 homes. A 100 MW battery was refused planning here in 2023; while discharging it could have supplied about 350,000 homes.
Ranks 276 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Hook Street - Energy Storage CompoundImmersa | Battery | 100 MW |
Refused by Stroud Council in 2023Who can move it: Stroud Council |
| Worlds End Solar FarmBritish Solar Renewables | Solar | 18,000 homes 50 MW |
Waiting 5.2 years for a planning decisionWho can move it: Stroud Council |
| Woodlands Farm, Clapton - Ground Mounted Solar ParkEcotricity Generation Limited | Solar | 13,000 homes 36 MW |
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 5 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Stroud compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call