CONSTITUENCY BRIEFING · ENERGYMAP.APP

South Cotswolds

MP: Dr Roz Savage (Liberal Democrat) England Data to July 2026

South Cotswolds has 194 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 70,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,511 homes.

Ranks 22 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Lime Down - Battery StorageIsland Green Power Battery
500 MW
Applied in 2025, still waiting for a decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects)
Lime Down - Solar ProjectIsland Green Power Solar 182,000 homes
500 MW
Applied in 2025, still waiting for a decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects)
Fairholme, Minety - Battery StoragePelagic Energy Battery
50 MW
Cannot connect to the grid until 2025, 1 years after it was approvedWho can move it: the grid operator (NESO) and National Grid

What else is in the briefing