Strangford
Strangford has 6 MW of renewables running, enough for 2,200 homes over a year, and nothing large waiting in the planning queue. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. Northern Ireland is on the all-Ireland grid, so Britain's grid bottlenecks do not reach bills here in the same way.
Ranks 525 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Carrickmannon Road, Ballygowan - Wind TurbineUnknown | Onshore wind | 8.8 MW7,700 homes | Waiting 2.2 years for a planning decisionWho can move it: Ards and North Down Council · planning ref LA06/2024/0473/F |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Strangford | 0.3 MW | 6 MW | not visible |
| South Down | 0.3 MW | 0.2 MW | not visible |
| Lagan Valley | 0.5 MW | 76 MW | not visible |
| Belfast South and Mid Down | 0.2 MW | 0 MW | not visible |
| Belfast East | 0 MW | 0 MW | not visible |
| North Down | 0 MW | 0 MW | not visible |
Lagan Valley next door has 0.5 MW waiting, more than Strangford's 0.3 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 1 story angles for local reporting