Staffordshire Moorlands has 13 MW of renewables running, enough for 4,900 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.5m across the constituency's 37,742 homes. A 99 MW battery was refused planning here in 2025; while discharging it could have supplied about 347,000 homes.

Ranks 510 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Cellarhead Substation, Rownall Road - Battery EnergyC&S Energy Limited Battery
400 MW
Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company
Cellarhead Substation, Rownall Road - Battery StoragS & C Energy Limited Battery
400 MW
Waiting 2.5 years for a planning decisionWho can move it: Staffordshire Moorlands Council
Leek Road, Werrington - Battery Energy StorageMasdar Arlington Energy Battery
300 MW
Applied in 2025, still waiting for a decisionWho can move it: Staffordshire Council