CONSTITUENCY BRIEFING · ENERGYMAP.APP

St Austell and Newquay

MP: Noah Law (Labour) England Data to July 2026

St Austell and Newquay has 11 MW of clean power (almost all onshore wind) approved and still not built: enough to supply a year's electricity to 8,900 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,478 homes.

Ranks 222 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Indian Queens National Grid Substation, Domelick HilEDF Energy Renewables (merged with Pivot Power Battery
50 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company
Indian Queens Sub station, Carne Hill - Battery EnerRenewable Connections Development Limited Battery
50 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Burthy Row Farm, Trefullock Moor - Solar Farm & BattJBM Solar Projects Limited Solar 18,000 homes
50 MW
Waiting 3.4 years for a planning decisionWho can move it: Cornwall Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.